Case Study

St John’s Primary & Nursery School

Project description

Installation of kitchen ventilation canopy and ductwork system linked to gas proving and monitoring system and installation of kitchen gas water and waste services. Boiler room replacement providing LTHW and DHW and a new control system to all areas within the school. The installation of new radiators complete with thermostatic radiator valves throughout the building together with localised ventilation and controls within all toilet areas.

Project details

Duration:
June 2011 for 9 months

Head of Projects:
Matt King